Project Plan
Contents
- 1 Work Package 1: Iterative Design of Compiler Framework
- 2 Work Package 2: Iterative Implementation of Compiler Framework
- 3 Work Package 3: Design and Build of Hardware Measurement Platform
- 4 Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development
- 5 Work Package 5: Theory of Analysis of Machine Learning Techniques
- 6 Work Package 6: Training and Testing Prototype Infrastructure
- 7 Work Package 7: Implement New Optimisation Passes
- 8 Work Package 8: Evaluation of Infrastructure
- 9 Work Package 9: Dissemination and Exploitation
- 10 Gantt Chart
Work Package 1: Iterative Design of Compiler Framework
Work Package 1: Iterative Design of Compiler Framework | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 31 August 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1.1 | Decision of GCC/LLVM for first implementation | E | Emb. | 31 Aug 2013 | Decision made to use GCC |
1.2 | Design doc for compiler integration | E | Emb. | 31 Aug 2013 | Live document, currently available via http://mageec.org/doxygen |
1.3 | Design doc for machine learning interface | E | Emb. | 31 Aug 2013 | Live document, currently available via http://mageec.org/doxygen |
1.4 | Design doc for feature selection | E | Emb. | 31 Aug 2013 | Live document, currently available via http://mageec.org/doxygen |
1.5 | Iterate 2-5 throughout project | E | Emb. | End of each Q. | Live deliverable continues to be updated with latest version. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
Work Package 2: Iterative Implementation of Compiler Framework
Work Package 2: Iterative Implementation of Compiler Framework | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
2.1 | First iteration of implementation, testing, documentation with GCC | E | Emb. | 30 Nov 2013 | Implementation has begun, source is available at https://github.com/mageec/mageec and documentation at http://mageec.org/doxygen |
2.2 | Second iteration of framework (using LLVM) | E | Emb. | 28 Feb 2014 | Early prototype demonstrated as part of informal workshop at [Euro LLVM] in April 2014. |
2.3 | Refinement of implementation with both compilers | E | Emb. | End of each Q. | Demonstration of full GCC version given at GNU Tools Cauldron, Cambridge, July 2014 (see https://gcc.gnu.org/wiki/cauldron2014). Demonstration of full LLVM version scheduled for NA LLVM Confererence, October 2014. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 3: Design and Build of Hardware Measurement Platform
Work Package 3: Design and Build of Hardware Measurement Platform | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 31 July 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
3.1 | Board Design Documentation | E | UoB | 31 Jul 2013 | Board designs and documentation available via Git repository. Deliverable 3.1 |
3.2 | Working Hardware | E | UoB | 31 Jul 2013 | Boards have been tested and demonstrated. Images can be found on Deliverable 3.2 |
3.3 | v2 Measuring Hardware | E | UoB | 31 Jan 2014 | Deliverable 3.3. Arrived Dec 11 2013 and made widely available with TSB help at EEC SIG workshop and FOSDEM. Second batch being made to support wider desire for evaluation end of September 2014. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development
Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 30 September 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
4.1 | Training set source | E | UoB | 30 Sep 2013 | Complete and available as part of BEEBS but with scope for additional benchmarks (Deliverable 4.1) |
4.2 | Case study source | E | UoB | 28 Feb 2014 | Possibilities being explored (Deliverable 4.2) |
4.3 | Embedded systems set up for testing | I | UoB | 30 Sep 2013 | Physical setup internal, documentation external. These boards have been tested using code from Deliverable 4.1, Pictures and Videos can be found here |
4.4 | Evaluation set of Test Programs | E | UoB | 28 Feb 2014 | Dedicated meetings set up to tackle this deliverable. |
4.5 | Enhancements to Training Set (BEEBS v2.0) | E | UoB | End of Each Q. | BEEBS v2.0 release date 5 September 2014, includes 80 benchmarks, but set increased by using data variants of some benchmarks and avaiable on http://beebs/eu. No further development is planned as part of MAGEEC, since we believe with data variants we have sufficient benchmarks. James Pallister is writing a paper summarizing all the analysis that has been carried out for BEEBS v2.0, due for completion by 30 Nov 2014, |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 5: Theory of Analysis of Machine Learning Techniques
Work Package 5: Theory of Analysis of Machine Learning Techniques | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 31 July 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
5.1 | Literature Review | E | UoB | 30 Sep 2013 (draft) ; 31 Dec 2013 (final) | May be appropriate for publication. Ongoing, references can be found on the Literature page. |
5.2 | Selection of core learning algorithm(s) | E | UoB | 30 Sep 2013 | Output of working days. Possible candidates identified for final selection (Deliverable 5.2). This BEEBS 2.0 and analysis which has led to choice of C4.5/C5.0 as the leaning algorithm |
5.3 | Training approach | E | UoB | 30 Sep 2013 | Output of working days, as per Deliverable 5.2 |
5.4 | API for implementers | E | UoB | 30 Sep 2013 | See Work Package 1. Plugin API used for GCC, Subclassing used for LLVM. |
5.5 | Review of initial approach | E | UoB | 31 July 2014 | Blog post by Greg Cawthorne, which may be suitable for future publication. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 6: Training and Testing Prototype Infrastructure
Work Package 6: Training and Testing Prototype Infrastructure | |||||
---|---|---|---|---|---|
Start date: 1 March 2014 End date: 31 May 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
6.1 | Working training infrastructure (existing optimisations) | E | Emb. | 31 May 2014 | First version developed, and highlighted need for: i) mechanism to determine per-function energy usage; 2) a way to reduce the number of data gathering runs; and 3) the importance of callibrating test boards before each run. Work in progress by Simon Cook to use cycle accurate models to determine apportioning of energy usage to functions. Blog post by George Field on reducing tests using Plackett-Burnham experiemental deisgn. Blog post to be written by James Pallister on callibration. |
6.2 | Results from proof of concept training and test (existing optimisations) | E | Emb. | 31 May 2014 | Demonstrated at GNU Tools Cauldron, July 2014 (see https://gcc.gnu.org/wiki/cauldron2014), but training set inadequate for good results. |
6.3 | Working training infrastructure (new optimisations) | E | Emb. | 31 May 2014 | New optimizations implementation now not expected in time (see [[}#WP7|Work Package 7]]). Focus is on refining data gathering for more robust training (see [[}#WP8|Work Package 8]]). |
6.4 | Results from proof of concept training and test (new optimisations) | E | Emb. | 31 May 2014 | As noted in deliverable 6.3, focus is on increased robustness. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 7: Implement New Optimisation Passes
Work Package 7: Implement New Optimisation Passes | |||||
---|---|---|---|---|---|
Start date: 1 September 2013 End date: 31 May 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
7.1 | Review of existing techniques for energy optimisation | E | Emb. | 31 Jan 2014 | co-located at UoB for knowledge exchange. Review of existing optimisation techniques for energy to appear as part of JP's 1st year PhD review. |
7.2 | Design optimisation passes | E | Emb. | 28 Feb 2014 | Theortical basis established and being presented at CASEs 2014 and Micro 47 (TBC) wich provide the requirements specification. Initial design for GCC begun. |
7.3 | Implement optimisation passes in GCC | E | Emb. | 28 Feb 2014 | Illness of the implementer, means this is now not likely to be implemented, or only at the very end of the project. We are considering whether simpler alternatives are worth implementing by someone else. |
7.4 | Implement optimisation passes in LLVM | E | Emb. | 31 May 2014 | Severly limited by failure of GCC work, on which this was to be based. We are considering whether simpler alternatives can be implemented. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 8: Evaluation of Infrastructure
Work Package 8: Evaluation of Infrastructure | |||||
---|---|---|---|---|---|
Start date: 1 June 2014 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
8.1 | Trained and tested complete system with full case studies | E | UoB | 30 Sep 2014 | Work in progress. Systems implemented to gather data for Atmel ATMega328 processors. Systems planned for ARM Cortex M3 processors. Case studies identified in Stoil Ganev's Blog post. Evaluation of ATMega328 will use a weather station, second case study is for MSP430, for which MAGEEC is not expected to have data in time. Third case study for ARM Cortex M3 identified as battery controller. |
8.2 | Draft paper presenting results | E | UoB | 30 Sep 2014 | Work in progress. |
8.3 | Final paper | E | Emb. | 30 Nov 2014 | This is the ultimate report and it is anticipated that it will take some time to develop. Additionally engineering on the project will continue whilst the paper is written, hence this will be a significantly large task. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
by Joern
Work Package 9: Dissemination and Exploitation
Work Package 9: Dissemination and Exploitation | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
9.1 | Exploitation plan | E | Emb. | 31 Aug 2013 | Updated every quarter |
9.2 | Participation in workshops and training events | E | Emb. | 30 Nov 2014 | Most recent full demo and presentaton given at the GNU Tools Cauldron, future events include North American Developers' Meeting and Innovate UK 2014. Full list at MAGEEC#Events. |
9.3 | Website/wiki/new media | E | Emb. | 31 Aug 2013 | Maintained throughout project, new website http://www.beebs.eu for BEEBS. |
9.4 | Papers | E | n/a | n/a | Detailed throughout project plan, for dates and details, refer to associated work packages. |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Gantt Chart
The following Gantt Chart details the interactions between work packages. As one work package does not necessarily depend on the entire completion of another, a traditional finish-start relationship does not perfectly represent this information. The Microsoft Project file used to generate this chart can be found at File:MAGEEC Gantt.mpp.