Milestones
From MAGEEC
Note: This does not include those which are recurring
Ref | Title | Work Package | Responsibility | Due Date | Cost to Milestone (£) | Notes |
---|---|---|---|---|---|---|
WP1/1 | Decision of GCC/LLVM for first implementation | WP1 | SC | 2013-08-31 | ||
WP1/2 | Design documentation for compiler integration, machine learning interface and available features | WP1 | SC | 2013-08-31 | Iterative design, live document | |
WP2/1 | First iteration of implementation, testing, documentation with first compiler | WP2 | SC | 2013-11-30 | ||
WP2/2 | Second iteration of development using second compiler | WP2 | SC | 2013-11-30 | ||
WP3/1 | Board Design Documentation | WP3 | 2013-07-31 | |||
WP3/2 | Working Hardware | WP3 | 2013-07-31 | |||
WP4/1 | Training set and case study sources | WP4 | 2013-09-30 | |||
WP4/2 | Embedded systems set up for testing | WP4 | 2013-09-30 | Physical setup internal, documentation external | ||
WP5/1 | Literature Review | WP5 | 2013-07-31 | May be appropriate for publication | ||
WP5/2 | Selection of core learning algorithm(s) and training approach | WP5 | 2013-08-31 | Output of working days | ||
WP5/3 | API for implementers | WP5 | 2013-09-30 | Output of working days | ||
WP5/4 | Review of approach | WP5 | 2013-12-31 | May be appropriate for publication | ||
WP6/1 | Paper identifying characteristics suitable for compiler optimisation passes | WP6 | 2013-08-31 | |||
WP7/1 | Working training infrastructure (existing optimisations) | WP7 | 2014-02-28 | |||
WP7/2 | Results from proof of concept training and test (existing optimisations) | WP7 | 2014-02-28 | This is proof of concept, not the evaluation | ||
WP7/3 | Working training infrastructure (new optimisations) | WP7 | 2014-05-31 | |||
WP7/4 | Results from proof of concept training and test (new optimisations) | WP7 | 2014-05-31 | This is proof of concept, not the evaluation | ||
WP8/1 | Design optimisation passes | WP8 | 2014-02-28 | |||
WP8/2 | Implement optimisation passes in GCC | WP8 | 2014-02-28 | |||
WP8/3 | Implement optimisation passes in LLVM | WP8 | 2014-05-31 | |||
WP9/1 | Trained and tested complete system with full case studies | WP9 | 2014-08-31 | |||
WP9/2 | Draft paper presenting results | WP9 | 2014-08-31 | |||
WP9/3 | Final paper | WP9 | 2014-11-30 | This is the ultimate report and it is anticipated that it will take some time to develop. |