− | Cost ''of'' milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as ''quarter effort''). The cost ''to'' milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package | + | Cost ''of'' milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as ''quarter effort''). The cost ''to'' milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package 9, these are ongoing throughout the project and have been allocated as such. |
{| class="wikitable sortable" width="100%" | {| class="wikitable sortable" width="100%" |
Revision as of 09:49, 26 April 2013
Cost of milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as quarter effort). The cost to milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package 9, these are ongoing throughout the project and have been allocated as such.
Ref | Title | Work Package | Responsibility | Due Date | Quarter Effort | Cost of Milestone (£) | Cost to Milestone (£) | Notes |
---|---|---|---|---|---|---|---|---|
WP3/1 | Board Design Documentation and working hardware | WP3 | UoB | 2013-07-31 | 100% | 17009.00 | 17009.00 | |
WP1/1 | Decision of GCC/LLVM for first implementation | WP1 | Emb. | 2013-08-31 | 35% | 5134.80 | 5134.80 | |
WP1/2 | Design documentation for compiler integration, machine learning interface and available features | WP1 | Emb. | 2013-08-31 | 65% | 9536.07 | 9536.07 | Iterative design, live document |
WP4/1 | Training set and case study sources | WP4 | UoB | 2013-09-30 | 33.3% | 2510.93 | 2510.93 | |
WP4/2 | Embedded systems set up for testing | WP4 | UoB | 2013-09-30 | 33.3% | 3010.93 | 22530.85 | Physical setup internal, documentation external |
WP5/2 | Selection of core learning algorithm(s), training approach and API | WP5 | UoB | 2013-09-30 | 33% | 2510.93 | 8212.45 | Output of working days |
WP2/1 | First and second iterations of implementation, testing, documentation with two compilers | WP2 | Emb. | 2013-11-30 | 100% | 10289.30 | 33172.62 | |
WP5/1 | Literature Review | WP5 | UoB | 2013-12-31 | 100% | 5701.53 | 5701.53 | May be appropriate for publication |
WP6/1 | Working training infrastructure (existing optimisations) | WP6 | Emb. | 2014-02-28 | 35% | 7556.52 | 7556.52 | |
WP6/2 | Results from proof of concept training and test (existing optimisations) | WP6 | Emb. | 2014-02-28 | 25% | 5397.51 | 68657.49 | This is proof of concept, not the evaluation |
WP7/1 | Design and implement optimisation passes in GCC | WP7 | Emb. | 2014-02-28 | 40% | 8636.02 | 8626.02 | |
WP6/3 | Working training infrastructure (new optimisations) | WP6 | Emb. | 2014-05-31 | 33.3% Emb, 50% UoB | 9579.99 | 86873.50 | |
WP6/4 | Results from proof of concept training and test (new optimisations) | WP6 | Emb. | 2014-05-31 | 33.3% Emb, 50% UoB | 9579.99 | 96453.50 | This is proof of concept, not the evaluation |
WP7/2 | Implement optimisation passes in LLVM | WP7 | Emb. | 2014-05-31 | 33.3% | 7171.74 | 15807.76 | |
WP5/3 | Review of approach | WP5 | UoB | 2014-07-31 | 33% | 8281.77 | 41454.38 | May be appropriate for publication |
WP8/1 | Trained and tested complete system with full case studies | WP8 | UoB | 2014-08-31 | 33.3% Emb, 50% UoB | 14030.86 | 109443.65 | |
WP8/2 | Draft paper presenting results | WP8 | UoB | 2014-08-31 | 33.3% Emb, 50% UoB | 14030.86 | 139968.72 | |
WP8/3 | Final paper with final modifications and result generation | WP8 | Emb. | 2014-11-30 | 100% Emb, 100% UoB | 25426.28 | 165395.00 | This is the ultimate report and it is anticipated that it will take some time to develop. |