Cost ''of'' milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as ''quarter effort''). The cost ''to'' milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package 10, these are ongoing throughout the project and thus have been allocated  
+
Cost ''of'' milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as ''quarter effort''). The cost ''to'' milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package 9, these are ongoing throughout the project and have been allocated as such.
  
 
{| class="wikitable sortable" width="100%"
 
{| class="wikitable sortable" width="100%"

Revision as of 09:49, 26 April 2013

Cost of milestones were calculated by taking the effort allocated per consortium member for the particular quarter the milestone is in and allocating a proportion of that quarter's costs based on the amount of effort required in that quarter (shown in the table as quarter effort). The cost to milestone is then calculated by using the projects Gantt Chart and calculating the cumulative costs of all work required for that milestone. For the costs attributed to Work Package 9, these are ongoing throughout the project and have been allocated as such.

Ref Title Work Package Responsibility Due Date Quarter Effort Cost of Milestone (£) Cost to Milestone (£) Notes
WP3/1 Board Design Documentation and working hardware WP3 UoB 2013-07-31 100% 17009.00 17009.00
WP1/1 Decision of GCC/LLVM for first implementation WP1 Emb. 2013-08-31 35% 5134.80 5134.80
WP1/2 Design documentation for compiler integration, machine learning interface and available features WP1 Emb. 2013-08-31 65% 9536.07 9536.07 Iterative design, live document
WP4/1 Training set and case study sources WP4 UoB 2013-09-30 33.3% 2510.93 2510.93
WP4/2 Embedded systems set up for testing WP4 UoB 2013-09-30 33.3% 3010.93 22530.85 Physical setup internal, documentation external
WP5/2 Selection of core learning algorithm(s), training approach and API WP5 UoB 2013-09-30 33% 2510.93 8212.45 Output of working days
WP2/1 First and second iterations of implementation, testing, documentation with two compilers WP2 Emb. 2013-11-30 100% 10289.30 33172.62
WP5/1 Literature Review WP5 UoB 2013-12-31 100% 5701.53 5701.53 May be appropriate for publication
WP6/1 Working training infrastructure (existing optimisations) WP6 Emb. 2014-02-28 35% 7556.52 7556.52
WP6/2 Results from proof of concept training and test (existing optimisations) WP6 Emb. 2014-02-28 25% 5397.51 68657.49 This is proof of concept, not the evaluation
WP7/1 Design and implement optimisation passes in GCC WP7 Emb. 2014-02-28 40% 8636.02 8626.02
WP6/3 Working training infrastructure (new optimisations) WP6 Emb. 2014-05-31 33.3% Emb, 50% UoB 9579.99 86873.50
WP6/4 Results from proof of concept training and test (new optimisations) WP6 Emb. 2014-05-31 33.3% Emb, 50% UoB 9579.99 96453.50 This is proof of concept, not the evaluation
WP7/2 Implement optimisation passes in LLVM WP7 Emb. 2014-05-31 33.3% 7171.74 15807.76
WP5/3 Review of approach WP5 UoB 2014-07-31 33% 8281.77 41454.38 May be appropriate for publication
WP8/1 Trained and tested complete system with full case studies WP8 UoB 2014-08-31 33.3% Emb, 50% UoB 14030.86 109443.65
WP8/2 Draft paper presenting results WP8 UoB 2014-08-31 33.3% Emb, 50% UoB 14030.86 139968.72
WP8/3 Final paper with final modifications and result generation WP8 Emb. 2014-11-30 100% Emb, 100% UoB 25426.28 165395.00 This is the ultimate report and it is anticipated that it will take some time to develop.