Difference between revisions of "Project Plan"
(Add WP9/1) |
m (Categorise page as Planning) |
||
Line 274: | Line 274: | ||
| dependents = | | dependents = | ||
}} | }} | ||
+ | |||
+ | [[Category:Planning]] |
Revision as of 16:11, 25 March 2013
Contents
- 1 Work Package 1: Iterative Design of Compiler Framework
- 2 Work Package 2: Iterative Implementation of Compiler Framework
- 3 Work Package 3: Design and Build of Hardware Measurement Platform
- 4 Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development
- 5 Work Package 5: Theory of Analysis of Machine Learning Techniques
- 6 Work Package 6: Theory of New Optimisation Passes
- 7 Work Package 7: Training Prototype Infrastructure
- 8 Work Package 8: Implement New Optimisation Passes
- 9 Work Package 9: Evaluation of Infrastructure
- 10 Work Package 10: Dissemination and Exploitation
Work Package 1: Iterative Design of Compiler Framework
Work Package 1: Iterative Design of Compiler Framework | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 31 August 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Decision of GCC/LLVM for first implementation | E | SC | 31 Aug 2013 | |
2 | Design doc for compiler integration | E | SC | 31 Aug 2013 | Iterative design, live document |
3 | Design doc for machine learning interface | E | SC | 31 Aug 2013 | Iterative design, live document |
4 | Design doc identifying available features | E | SC | 31 Aug 2013 | Iterative design, live document |
5 | Iterate 2-5 throughout project | E | SC | End of each Q. | |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
Work Package 2: Iterative Implementation of Compiler Framework
Work Package 2: Iterative Implementation of Compiler Framework | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | First iteration of implementation, testing, documentation with first compiler | E | SC | 30 Nov 2013 | |
2 | Second iteration of development using second compiler | E | SC | 30 Nov 2013 | |
3 | Refinement of implementation with both compilers | E | SC | End of each Q. | |
Dependencies | |||||
Items which must be available for this Work Package | |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 3: Design and Build of Hardware Measurement Platform
Work Package 3: Design and Build of Hardware Measurement Platform | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 31 July 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Board Design Documentation | E | 31 Jul 2013 | ||
2 | Working Hardware | E | 31 Jul 2013 | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development
Work Package 4: Training Set, Test Program, Test Hardware and Case Study Development | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 30 September 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Training set source | E | |||
2 | Case study source | E | |||
3 | Embedded systems set up for testing | I | Physical setup internal, documentation external | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 5: Theory of Analysis of Machine Learning Techniques
Work Package 5: Theory of Analysis of Machine Learning Techniques | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 31 August 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Literature Review | E | 31 Jul 2013 | May be appropriate for publication | |
2 | Selection of core learning algorithm(s) | 31 Aug 2013 | Output of working days | ||
3 | Training approach | 31 Aug 2013 | Output of working days | ||
4 | API for implementers | 30 Sep 2013 | Output of working days | ||
5 | Review of approach | 31 Dec 2013 | May be appropriate for publication | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 6: Theory of New Optimisation Passes
Work Package 6: Theory of New Optimisation Passes | |||||
---|---|---|---|---|---|
Start date: 1 July 2013 End date: 31 August 2013 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Paper identifying characteristics suitable for compiler optimisation passes | E | 31 Aug 2013 | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 7: Training Prototype Infrastructure
Work Package 7: Training Prototype Infrastructure | |||||
---|---|---|---|---|---|
Start date: 1 March 2014 End date: 31 May 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Working training infrastructure (existing optimisations) | E | 28 Feb 2014 | ||
2 | Results from proof of concept training and test (existing optimisations) | E | 28 Feb 2014 | This is proof of concept, not the evaluation | |
3 | Working training infrastructure (new optimisations) | E | 31 May 2014 | ||
4 | Results from proof of concept training and test (new optimisations) | E | 31 May 2014 | This is proof of concept, not the evaluation | |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 8: Implement New Optimisation Passes
Work Package 8: Implement New Optimisation Passes | |||||
---|---|---|---|---|---|
Start date: 1 September 2013 End date: 31 May 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Design optimisation passes | E | 28 Feb 2014 | ||
2 | Implement optimisation passes in GCC | E | 28 Feb 2014 | ||
3 | Implement optimisation passes in LLVM | E | 31 May 2014 | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 9: Evaluation of Infrastructure
Work Package 9: Evaluation of Infrastructure | |||||
---|---|---|---|---|---|
Start date: 1 June 2014 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Trained and tested complete system with full case studies | E | 31 Aug 2014 | ||
2 | Draft paper presenting results | E | 31 Aug 2014 | ||
3 | Final paper | E | 30 Nov 2014 | This is the ultimate report and it is anticipated that it will take some time to develop. | |
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|
Work Package 10: Dissemination and Exploitation
Work Package 10: Dissemination and Exploitation | |||||
---|---|---|---|---|---|
Start date: 1 June 2013 End date: 30 Nov 2014 | |||||
Work Package Objectives:
| |||||
Description of Work
| |||||
Equipment and Facilities
| |||||
Summary of Deliverables | |||||
Ref. | Title | Int/Ext | Responsiblity | Due Date | Comments/Notes |
1 | Exploitation plan | E | 31 Aug 2013 | Updated every quarter | |
2 | Participation in workshops and training events | E | 30 Nov 2014 | Dates to be confirmed | |
3 | Website/wiki/new media | E | 31 Aug 2013 | Due date is set up of, mainted throughout project | |
4 | Papers | E | Detailed throughout project plan, for dates and details, refer to associated work packages. | ||
Dependencies | |||||
Items which must be available for this Work Package | |||||
| |||||
Work Packages dependent on this Work Package | |||||
|